## 1) Light Customization (Existing common molds; only modify logo, anodizing color, packaging, lens / LED; no changes to structure or driver)
This is the fastest option. You may send an email directly to LIGHTFE.
- Sampling: 5‑7 working days
- Mass production after sample confirmation: 15‑25 working days
- Total lead time: 20‑32 working days
Suitable for ODM projects. The housing structure and driver board are off‑the‑shelf; only minor adjustments are made to appearance, silk‑screen printing and accessories. Low MOQ applies.
## 2) Moderate Customization (Modify structure, redesign driver PCBs, adjust optical beam based on existing common housing molds; no new aluminum mold development)
- Solution & drawing development: 3‑7 working days
- Prototype / CNC sampling, debugging and aging test: 10‑20 working days (including driver revision, heat dissipation and waterproofing validation)
- Mass production after sample confirmation: 25‑35 working days
- Total lead time: 40‑60 working days
Suitable for customizing output modes, color temperature, charging solutions and head structures on proven flashlight bodies, without developing a full set of new housing molds.
## 3) Fully Custom ODM/OEM (From‑scratch ID & structural design, complete new aluminum housing mold development, brand‑new driver, optics and sealing design)
This option has the longest lead time.
1. ID, structure, BOM and PCB schematic design: 10‑20 working days
2. CNC prototyping and multi‑round testing (luminous efficiency, temperature rise, waterproofing, drop test), including revision iterations: 15‑30 working days
3. Aluminum mold development (extrusion / turning molds) plus mold trial and revision: 25‑40 working days (major bottleneck of the whole project)
4. Small‑batch pilot production validation: 7‑14 working days
5. Formal mass production: 30‑45 working days
Total project timeline from project initiation to bulk delivery: **90‑150 working days**.
Complex models (titanium alloy, special spectrum, high‑reliability IP68 rating, with certifications) may extend the cycle to 180 working days.
## Key Factors Affecting Lead Time
1. Number of revisions: Each round of repeated sample modification adds 7‑15 working days. Freezing BOM and drawings in advance saves substantial time.
2. Material lead time: Stock shortages of custom LEDs, lenses, special‑purpose ICs and sealing components will cause delays.
3. Certifications: CE, RoHS, explosion‑proof and other certifications add an extra 20‑40 working days.
4. Material selection: Lead‑time ranking: titanium alloy > stainless steel > aluminum alloy. Titanium alloy requires much longer CNC machining and anodizing cycles.
5. Order volume: Large orders require extended scheduling and aging‑test duration.
### Quick Reference Summary
- Logo printing & color change: ~ 1 month
- Driver and optics modification without new housing molds: ~ 2 months
- Brand‑new appearance with full mold development: 3‑5 months
Products